Question: table [ [ Activity , Immediate Predecessor,Normal Duration ] , [ A , None, 6 weeks ] , [ B , A , 3

\table[[Activity,Immediate Predecessor,Normal Duration],[A,None,6 weeks],[B,A,3 weeks],[C,A,3 weeks],[D,B , C,7 weeks],[E,C,6 weeks],[F,D, E,2 weeks]]
Draw the project network for the above information.
(5 marks)
Explain with example what is the critical path?
(5 marks)
Based on the above information and Table below, crash the project by 2 weeks (1 week at a time), indicating which activities should be crashed each week and what the effect is on the total project cost.
(10 marks)
 \table[[Activity,Immediate Predecessor,Normal Duration],[A,None,6 weeks],[B,A,3 weeks],[C,A,3 weeks],[D,B , C,7 weeks],[E,C,6 weeks],[F,D, E,2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!