Question: table [ [ Activity , Immediate Predecessor,Normal Duration ] , [ A , None, 6 weeks ] , [ B , A , 3
tableActivityImmediate Predecessor,Normal DurationANone, weeksBA weeksCA weeksDB C weeksEC weeksFD E weeks
Draw the project network for the above information.
marks
Explain with example what is the critical path?
marks
Based on the above information and Table below, crash the project by weeks week at a time indicating which activities should be crashed each week and what the effect is on the total project cost.
marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
