Question: table [ [ Activity , Predecessor ( s ) , Duration ( days ) ] , [ A , - - , 5 ]

\table[[Activity,Predecessor(s),Duration (days)],[A,--,5],[B,A,20],[C,A,15],[D,A,5],[E,B, C,60],[F,D,15],[G,E,15],[H,E,22],[I,F, G, H,2]]
Figure 7-6 Network Scheduling Data
Consider the network scheduling data provided in Figure 7-6. Which activities constitute the critical pat for this project network?
Select one:
a.A-D-F-I
b. A-C-E-H-I
c.A-B-E-H-I
d. A-B-E-G-I
 \table[[Activity,Predecessor(s),Duration (days)],[A,--,5],[B,A,20],[C,A,15],[D,A,5],[E,B, C,60],[F,D,15],[G,E,15],[H,E,22],[I,F, G, H,2]] Figure 7-6 Network Scheduling Data Consider