Question: table reads: A Systems None 5 B Subsystem A design A 5 C Subsystem B design A 5 D Subsystem C design A 5 E
table reads:
A Systems None 5
B Subsystem A design A 5
C Subsystem B design A 5
D Subsystem C design A 5
E Program A B 4
F Program B C 4
G Program C D 4
H Subsystem A E 1
I Subsystem B F 1
J Subsystem C G 1
K Integration H, I, J 2
L Integration test K 2
QUESTIONS READ:
The project will take days.
The early start on Activity D is days.
The late start on Activity E is days.
The late finish on Activity I is days.
Calculate the free slack and total slack for all noncritical activities
(Click to select)
How sensitive is the network schedule?
(Click to select)
14