Question: table [ [ Task , Immediate Predecessor ( s ) , Duration ( days ) ] , [ A , None, 2 ] ,
tableTaskImmediate PredecessorsDuration daysANone,BNone,CADBEC DFD
a Draw the Network diagram and include the Early Starts ES Early Finishes EF Late Starts LS and Late Finishes LF points
b What is the expected completion time of this project? points
c What is the critical path through this project? points
d How much slack is in Activity C What does this mean? points
e How much slack is in Activity E points