Question: Task 1 : Complete the baseline budget for this project. Assume that the budget for an activity is used uniformly during its duration. Project: CRM
Task : Complete the baseline budget for this project. Assume that the budget for an activity is used
uniformly during its duration.
Project: CRM Budget
Assess User Requirements $
Assess Current System $
Specify System Requirements $
Send RFP for Software Vendors $
Send RFP for Hardware Vendors $
Select Software Vendor $
Select Hardware Vendor $
Program and Test the Module $
Train Users $
Cumulative
What is the budget at completion for this project?
What is the expected completion time for this project?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
