Question: Task 1 : Complete the baseline budget for this project. Assume that the budget for an activity is used uniformly during its duration. Project: CRM

Task 1: Complete the baseline budget for this project. Assume that the budget for an activity is used
uniformly during its duration.
Project: CRM Budget 123456789101112131415161718192021222324252627
Assess User Requirements $24,000
Assess Current System $16,000
Specify System Requirements $32,000
Send RFP for Software Vendors $10,000
Send RFP for Hardware Vendors $10,000
Select Software Vendor $4,000
Select Hardware Vendor $3,000
Program and Test the Module $150,000
Train Users $75,000
Cumulative
What is the budget at completion for this project?
What is the expected completion time for this project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!