Question: Task Duration Dependencies TI 10 T2 15 TI T3 10 TI, T2 T4 20 TS 10 T6 15 T3, T4 TZ 20 T3 TB 35

 Task Duration Dependencies TI 10 T2 15 TI T3 10 TI,

Task Duration Dependencies TI 10 T2 15 TI T3 10 TI, T2 T4 20 TS 10 T6 15 T3, T4 TZ 20 T3 TB 35 T9 15 T6 T10 5 T5, T9 TIL 10 T9 T12 20 T10 T13 35 T3, T4 T14 10 T8, T9 T15 20 Figure 23.14 Scheduling example T12, T14 T15 T16 10 23.6. Figure 23.14 shows the task durations for software project activities. Assume that a serious, unanticipated setback occurs, and instead of taking 10 days, task T5 takes 40 days. Draw up new bar charts showing how the project might be reorganized