Question: Task time estimates for a production line setup project at a factory are as follows: (Round your calculations to one decimal place) Activity Immediate Activity

Task time estimates for a production line setup
Task time estimates for a production line setup project at a factory are as follows: (Round your calculations to one decimal place) Activity Immediate Activity Predecessor(S) Time (days) A 6.0 B 7.2 C A 5.0 D B, C 6.0 E B, C 4.5 F D 7.7 G E,F 4.0 Draw the project using AON. (5 Points) Calculate the ES, EF, LS, LF for all the activities (5 Points) Calculate the slack for all the activities (5 Points) Identify the critical path (5 Points) What is the expected project length (5 Points)