Question: Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: Activity Time ( in hours ) Immediate Predecessor

Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows:
Activity
Time
(in hours)
Immediate Predecessor(s)
A
7.0
long dash
B
7.5
long dash
C
5.0
A
D
6.0
B, C
E
5.1
B, C
F
8.4
D
G
5.0
E, F