Question: Task time estimates for a production line setup project Robert Klassens Ontario factory are as follows: a) Draw the project network using AON.b) Identify the

Task time estimates for a production line setup project Robert Klassens Ontario factory are as follows: a) Draw the project network using AON.b) Identify the critical path.c) What is the expected project length? d) Draw a Gantt chart for the project.

Activity Time Immediate Predecessors
A 6.0 ---
B 7.2 --
C 5.0 A
D 6.0 B,C
E 4.5 B,C
F 7.7 D
G 4.0 E,F