Question: Task time estimates for a production line setup project Robert Klassens Ontario factory are as follows: a) Draw the project network using AON.b) Identify the
Task time estimates for a production line setup project Robert Klassens Ontario factory are as follows: a) Draw the project network using AON.b) Identify the critical path.c) What is the expected project length? d) Draw a Gantt chart for the project.
| Activity | Time | Immediate Predecessors |
| A | 6.0 | --- |
| B | 7.2 | -- |
| C | 5.0 | A |
| D | 6.0 | B,C |
| E | 4.5 | B,C |
| F | 7.7 | D |