Question: bask time estimates for a production line setup project Robert Klassen s Ontario factory are as follows: a ) Draw the project network using AON.b
bask time estimates for a production line setup project Robert Klassens Ontario factory are as follows: a Draw the project network using AON.b Identify the critical path.c What is the expected project length? d Draw a Gantt chart for the project.
Activity Time Immediate Predecessors
A
B
C A
D BC
E BC
F D
G EF