Question: The batches must be routed through five operations to complete the processing of the parts. Average batch quantity = 1 0 0 units, average setup

The batches must be routed through five operations to complete the processing
of the parts. Average batch quantity =100 units, average setup time =3.0 hr per batch,
number of operations per batch are 5 and average operation time is 8 min per piece
for the population of parts made in the plant. Nonoperation time is 7.5 hr. The plant
has 20 production machines that are 100% utilized (setup and run time), and the
machine operates 45 hr/wk. Determine:
(a) Weekly plant production rate
(b) Work-in-process for the plant.
3.4 How would you define the term manufacturing lead time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!