Question: The critical path for the network activities shown below is with duration table [ [ Activity , Duration,Predecessors ] , [ A , 4

The critical path for the network activities shown below is with duration
\table[[Activity,Duration,Predecessors],[A,4,--],[B,3,A],[C,9,--],[D,4,A],[E,5,B,C,D]]
CE; 14
ADE; 13
ABDE; 16
ABCDE; 25
ABE; 15
 The critical path for the network activities shown below is with