Question: The critical path for the network activities shown below is with duration table [ [ Activity , Duration,Predecessors ] , [ A , 1

The critical path for the network activities shown below is with duration
\table[[Activity,Duration,Predecessors],[A,10,--],[B,8,-],[C,4,A],[D,7,A,B],[E,6,C,D]]
ACDE; 27
ADE; 23
ACE; 20
ABCDE: 35
BDE; 21