Question: The critical path for the network activities shown below is with duration table [ [ Activity , Duration, table [ [ Immediate ]

The critical path for the network activities shown below is with duration
\table[[Activity,Duration,\table[[Immediate],[Predecessors]]],[A,4,-],[B,2,A],[C,9,-],[D,4,A],[E,5,B, C, D]]
A.A-B-E;11
B. A-D-E; 13
C. C-E; 14
D. A-B-C-D-E;24
E. A-B-D;10