Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 10 minus B 8 minus C
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 10 | minus |
| B | 8 | minus |
| C | 4 | A |
| D | 2 | A |
| E | 6 | B, C, D |
A. A-C-E; 20
B. A-B-D-E; 26
C. B-E; 14
D. A-D-E; 18
E. None of the Above
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
