Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 10 minus B 8 minus C
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 10 | minus |
| B | 8 | minus |
| C | 4 | A |
| D | 2 | A |
| E | 6 | B, C, D |
Part 2
A.
B-E; 14
B.
A-B-D-E; 26
C.
A-D-E; 18
D.
A-C-E; 20
E.
None of the above.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
