Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 10 minus B 8 minus C

The critical path for the network activities shown below is ________ with duration ________.

Activity

Duration

Immediate

Predecessors

A

10

minus

B

8

minus

C

4

A

D

2

A

E

6

B, C, D

Part 2

A.

B-E; 14

B.

A-B-D-E; 26

C.

A-D-E; 18

D.

A-C-E; 20

E.

None of the above.