Question: The critical path for the network activities shown below is ____ with duration ____. Activity Duration Immediate Predecessors A 10 -- B 8 -- C

The critical path for the network activities shown below is ____ with duration ____.

Activity

Duration

Immediate

Predecessors

A

10

--

B

8

--

C

4

A

D

2

A

E

6

B,C,D

A) A-C-E; 20

B) A-D-E; 18

C) B-E; 14

D) A-B-D-E; 26

E) none of the above