Question: The critical path for the network activities shown below is ____ with duration ____. Activity Duration Immediate Predecessors A 10 -- B 8 -- C
The critical path for the network activities shown below is ____ with duration ____.
| Activity | Duration | Immediate Predecessors |
| A | 10 | -- |
| B | 8 | -- |
| C | 4 | A |
| D | 2 | A |
| E | 6 | B,C,D |
A) A-C-E; 20
B) A-D-E; 18
C) B-E; 14
D) A-B-D-E; 26
E) none of the above
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
