Question: The critical path for the network activities shown below is with duration Activity Duration (Week) Immediate Predecessors 2 B 4 6 , D 1 .

The critical path for the network activities
The critical path for the network activities shown below is with duration Activity Duration (Week) Immediate Predecessors 2 B 4 6 , D 1 . EN 2 B, C, D B-C-E; 12 weeks B-D-E; 7 weeks A-D-E; 5 weeks OB-E: 6 weeks O A-C-E: 10 weeks