Question: 9. The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4 B 2 A C
9. The critical path for the network activities shown below is ________ with duration ________.
| Activity |
Duration | Immediate Predecessors |
| A | 4 | |
| B | 2 | A |
| C | 7 | |
| D | 4 | A |
| E | 5 | B, C, D |
A) A-B-D; 10
B) A-B-E; 11
C) C-E; 12
D) A-D-E; 13
E) A-B-C-D-E; 22
please explain shortly