Question: The critical path for the network activities shown below is with duration table [ [ Activity , Duration, table [ [ Immediate ]

The critical path for the network activities shown below is with duration
\table[[Activity,Duration,\table[[Immediate],[Predecessors]]],[A,10,-],[B,8,-],[C,4,A],[D,2,A],[E,6,B, C, D]]
A.B-E;14
B. A-B-D-E; 26
C. A-C-E; 20
D. A-D-E; 18
E. None of the above.