Question: The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U.
The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers).
| Week | Lead Time | ||||||||
| Item | 1 | 2 | 3 | 4 | 5 | 6 | 7 | (weeks) | |
| S | Gross req | nothing | 2 | ||||||
| On hand | nothing | ||||||||
| Net req | nothing | ||||||||
| Order receipt | nothing | ||||||||
| Order release | nothing | ||||||||
| Item | On-Hand Inventory | Item | On-Hand Inventory |
| S | 20 | W | 30 |
| T | 20 | X | 25 |
| U | 40 | Y | 240 |
| V | 30 | Z | 40 |