Question: The direct materials and direct labour standards for one bottle of Clean-All spray cleaner are given below: Standard Quantity or Hours Standard Price or Rate

The direct materials and direct labour standards for one bottle of Clean-All spray cleaner are given below:

Standard Quantity or Hours Standard Price or Rate StandardCost

Direct materials 7.0millilitres $0.34per milliliter $2.38

Direct labour 0.2hours $12.00per hour $2.40

During the most recent month, the following activity was recorded:

a. 24,500 millilitres of material was purchased at a cost of $0.29 per milliliter

b. All of the material was used to produce 3,000 bottles of Clean-All.

c.675 hours of direct labour time was recorded at a total labour cost of $8,100.

Required:

1.Compute the direct materials price and quantity variances for the month.(Indicate the effect of each variance by selecting "F" for favourable, "U" for unfavourable, and "None" for no effect (i.e., zero variance).)

Materials price variance ??? ???

Materials quantity variance ??? ???

2.Compute the direct labour rate and efficiency variances for the month.(Indicate the effect of each variance by selecting "F" for favourable, "U" for unfavourable, and "None" for no effect (i.e., zero variance).)

Labour rate variance ??? ???

Labour efficiency variance ??? ???

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock