Question: The following data have been collected for a management information system project. Compute the SV and CV for period 6, 8, and 10. You should

The following data have been collected for a management information system project.

  1. Compute the SV and CV for period 6, 8, and 10. You should complete Earned Value Management Table.
  2. Compute the SPI, CPI, EAC, VAC, PCIB, TCPI for period 6, 8, and 10. You should complete Summary of EVM Parameters Table. Interpret the results.
  3. draw an appropriate graph to compare CPI and SPI.The following data have been collected for a

The following data have been collected for a

The following data have been collected for a

The following data have been collected for a

un 13 15 19 B G 2 2 0 0 7 7 8 15 15 4 19 A 0 5 5 11 11 15 19 23 A E H 0 0 0 0 0 0 0 0 0 5 5 un 6 11 11 4 15 19 st 23 un 9 9 17 D 2 2 N N 7 4 11 11 00 19 Task Weekly Cost A N 2 2 1 1 B 55 5 5555 5 C 5 5 7 8 3 N D 5 5 5 E 10 | 10 | 10 10 F 10 10 10 10 55 5 5 G55 5 5 5 un H 10 10 5 5 Summary of EVM Parameters SPI EAC VAC Project % Complete Period 6 Period 8 Period 10 Earned Value Management Table Period 6 Task EV PV SV % Complete Finish 25% AC 10 A B ws no C 33% D 0% 37 Cumulative Totals Period 8 Task EV AC PV CV SV % Complete Finish A 10 B 30% 20 60% 25 D 0% 0 55 Cumulative Totals Period 10 Task EV AC PV CV SV A % Complete Finish 60% 10 B 30 40 D Finish 50% 0% 20 E 0 F 30% 24 Cumulative Totals 124

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!