Question: The following table represents a project that should be scheduled using CPM Activity Immediate Predecessors Activity Duration (Days) A -- 3 B A 4 C
The following table represents a project that should be scheduled using CPM
| Activity | Immediate Predecessors | Activity Duration (Days) |
| A | -- | 3 |
| B | A | 4 |
| C | A | 5 |
| D | B,C | 3 |
| E | C | 4 |
| F | D,E | 4 |
The critical path is and its length is days.
The project completion time is days.