Question: The following table represents a project that should be scheduled using CPM Activity Immediate Predecessors Activity Duration (Days) A -- 3 B A 7 C
The following table represents a project that should be scheduled using CPM
Activity | Immediate Predecessors | Activity Duration (Days) |
A | -- | 3 |
B | A | 7 |
C | A | 5 |
D | B,C | 3 |
E | C | 4 |
F | D,E | 4 |
The critical path is and its length is days.
The project completion time is ______days.