Question: The following table represents a project that should be scheduled using CPM Activity Immediate Predecessors Activity Duration (Days) A -- 5 B A 3 C
The following table represents a project that should be scheduled using CPM
| Activity | Immediate Predecessors | Activity Duration (Days) |
| A | -- | 5 |
| B | A | 3 |
| C | A | 5 |
| D | B,C | 3 |
| E | C | 4 |
| F | D,E | 5 |
The critical path is _____ and its length is ______ days.
The project completion time is _____ days. (No , or - in critical path. Just write ABCD instead of A,B,C,D or A-B-C-D.)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock