The following table represents a project that should be scheduled using CPM

Activity Immediate Predecessors Activity Duration (Days)
A -- 5
B A 3
C A 5
D B,C 3
E C 4
F D,E 5

The critical path is _____ and its length is ______ days.

The project completion time is _____ days. (No , or - in critical path. Just write ABCD instead of A,B,C,D or A-B-C-D.)