Question: The information about a project with 10 activities is shown below. Activity A; 11 days; IP = none Activity B; 13 days; IP = none

The information about a project with 10
The information about a project with 10 activities is shown below. Activity A; 11 days; IP = none Activity B; 13 days; IP = none Activity C; 29 days; IP = A Activity D; 34 days; IP = A, B Activity E; 23 days; IP = B Activity F; 12 days; IP = C, D Activity G; 22 days; IP = C, D Activity H; 41 days; IP = E Activity K; 8 days; IP = F Activity M; 24 days; IP = G, H The earliest finish time of activity M is at the end of day