Question: The information about a project with 10 activities is shown below. Activity A; 7 days; IP = none Activity B; 12 days; IP = none

The information about a project with 10
The information about a project with 10 activities is shown below. Activity A; 7 days; IP = none Activity B; 12 days; IP = none Activity C; 18 days; IP = A Activity D; 18 days; IP = A, B Activity E; 15 days; IP = B Activity F; 32 days; IP = C Activity G; 25 days; IP =D Activity H; 31 days; IP = E Activity K; 19 days; IP = F, G Activity M; 21 days; IP = G, H ---- The earliest start time of activity K is at the end of day_