Question: Question 1 The information for a project is given in the Table below (time in weeks): Activity Immediate predecessors Most Likely time Pessimistic time A

Question 1 The information for a project is given

Question 1 The information for a project is given in the Table below (time in weeks): Activity Immediate predecessors Most Likely time Pessimistic time A Optimistic time 2 8 7 3 4 A 8 B 8 11 A 9 D 6 6 6 E 9 10 13 11 16 F 10 G A B, C D F, E G, F HI 6 10 13 H 10 14 16 14 I 6 7 7 J 6 8 a) Draw a network for this project b) Determine the critical path c) Determine the earliest and latest activity times d) Determine slack time for each activity