Question: The manager at Ormonde Inc. collected the value stream mapping data from the plant's most problematic manufacturing cell that fabricates parts for washing machines. This

The manager at Ormonde Inc. collected the value stream mapping data from the plant's most problematic manufacturing cell that fabricates parts for washing machines. This data is shown in Table 1. Using this data, calculate the current state performance of the cell and answer the following questions.
LOADING... Click the icon to view Table 1.
Part 2
a. What is the cell's current inventory level?
The cell's current inventory level is
2050 parts. (Enter your response as a whole number.)
Part 3
b. What is the takt time for this manufacturing cell?
The takt time is
2.81 minutes. (Enter your response rounded to two decimal places.)
Part 4
c. What is the production lead time at each process in the manufacturing cell?
Complete the table (Enter your responses rounded to two decimal places.)
Interval
Lead time
Before Cutting
.75 days
Between Cutting and Bending
.97 days
Between Bending and Punching
.32 days
After Punching
2.37 days
Part 5
d. What is the total processing time of this manufacturing cell?
The cell's total processing time is
550 seconds. (Enter your response as a whole number.)
Part 6
e. What is the capacity of this manufacturing cell?
The cell's capacity is
470 units.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!