Question: The manager at Ormonde Inc. collected the value stream mapping data from the plant's most problematic manufacturing cell that fabricates parts for washing machines. This
The manager at Ormonde Inc. collected the value stream mapping data from the plant's most problematic manufacturing cell that fabricates parts for washing machines. This data is shown in Table 1. Using this data, calculate the current state performance of the cell and answer the following questions.

| Overall Process Attributes | Average demand: 565/day Batch size: 30 Number of shifts per day: 3 Availability:8 hours per shift with a45 minute lunch break | |
| Process Step 1 | Cutting | Cycle time=126 secondsSetuptime=4 minutes Uptime=100% Operators=1 WIP=350 units (before Cutting) |
| Process Step 2 | Bending | Cycle time=240 secondsSetuptime=7 minutes Uptime=97% Operators=2 WIP=500 units (before Bending) |
| Process Step 3 | Punching | Cycle time=130 secondsSetuptime=none Uptime=100% Operators=1 WIP=250 units (Before Punching)WIP=1,200 units (After Punching) |
| Supplier Information | One shipment of 2,825 units each week | |
| Information Flow | All communications with customer are electronic There is a weekly order release to Cutting All material is pushed | |
a. What is the cell's current inventory level? b. What is the takt time for this manufacturing cell? c. What is the production lead time at each process in the manufacturing cell? d. What is the total processing time of this manufacturing cell? e. What is the capacity of this manufacturing cell? TADIEL ODEDATION DATA COD ODMONDE INO