Question: The overall average on a process you are attempting to monitor is 50.0 units. The process population standard deviation is 1.84 . Sample size is
The overall average on a process you are attempting to monitor is 50.0 units. The process population standard deviation is 1.84 . Sample size is given to be 16.
a) determine the 3-sigma x-chart control limits
Upper Control Limit (UCLx)= ___ units
Lower Control Limit (LCLx)= __ units
b) Now determine the 2-sigma x-chart control limits.
Upper Control Limit (UCLx)= __ units (round your response to two decimal places).
Lower Control Limit (LCLx)= ___ units (round your response to two decimal places).
c. How do the control limits change? (choose one)
A.The control limits for the 2-sigma x-chart and for the 3-sigma -chart are the same.
B.The control limits are tighter for the 2-sigma x-chart than for the 3-sigma x-chart.
C.The control limits are tighter for the 3-sigma x-chart than for the 2-sigma x-chart