Question: The primary Critical Path is: a . The path in which the Total Float is less than zero b . The path where the Late
The primary Critical Path is:
a The path in which the Total Float is less than zero
b The path where the Late Finish date exceeds the baseline finish date
c The path with the greatest total cost risk
d The path with the least amount of Total Float