Question: The process cycle time is 70 weeks. Slipway outfitting and quay outfitting have equal and most extended process times (21 weeks each). All other stations

  • The process cycle time is 70 weeks.
  • Slipway outfitting and quay outfitting have equal and most extended process times (21 weeks each).
  • All other stations have different process times in weeks or multiples (all integers).

QUESTION: Draw the assembly line. Show names and process times and calculate the capacity of the shipyard.

The process cycle time is 70 weeks. Slipway

panel construction section assembly pre-outfitting painting block building erection quay outfitting