Question: The project described by: Activity Immediate Predecessor Time ( days ) A - - 1 0 B A 4 C A 6 D B ,

The project described by:
Activity Immediate
Predecessor Time
(days)
A --10
B A 4
C A 6
D B, C 7
E C 5
has a critical path of length of