Question: The project described by: Activity Immediate Predecessor Time (days) A -- 10 B A 4 C A 6 D B 7 E C 5 is
The project described by:
| Activity | Immediate Predecessor | Time (days) |
| A | -- | 10 |
| B | A | 4 |
| C | A | 6 |
| D | B | 7 |
| E | C | 5 |
is best represented by which of the following networks?