Question: The project described by: Activity Immediate Predecessor Time (days) A -- 10 B A 4 C A 6 D B 7 E C 5 is

The project described by:

Activity Immediate Predecessor Time (days)
A -- 10
B A 4
C A 6
D B 7
E C 5

is best represented by which of the following networks?