Question: The project described by: Activity Immediate Predecessor Time (days) A -- 6 B A 2 C -- 8 D B, C 5 E D 7

The project described by:

Activity Immediate Predecessor Time (days)
A -- 6
B A 2
C -- 8
D B, C 5
E D 7

has a critical path of length of

Group of answer choices

15 days.

17 days.

18 days.

20 days.