Question: The Project Manager is about to begin a project comprised of the following six activities: DURATION ESTIMATES (days) ACTIVITY PRECEDES OPTIMISTIC MOST LIKELY PESSIMISTIC A
The Project Manager is about to begin a project comprised of the following six activities: DURATION ESTIMATES (days) ACTIVITY PRECEDES OPTIMISTIC MOST LIKELY PESSIMISTIC A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 What is the estimated slack time for the path A-D-F? Select one: A. 60 days B. 40 days C. 20 days D. 0 days E. 100 days?