Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start , A 82 0.37 B E 74 0.25

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start , A 82 0.37 B E 74 0.25 D 40 0.17 D End 14 0.46 E End 10 0.75 What is the probability that the project will be completed within 140 days? O a 1 Ob 0 Oc. 0.82 Od 0.18 O e 0.25