Question: There are four paths that lead to the final activity, G, which is the completion of a project. The length of the paths are as

There are four paths that lead to the final
There are four paths that lead to the final activity, G, which is the completion of a project. The length of the paths are as follows: (i) abdg: 4 weeks; (ii) acdeg: 5 weeks; (iii) afg: 6 weeks; (iv) abeg: 3 weeks. The earliest time that the project can be completed is: A. 4 weeks B. 5 weeks C. 3 weeks D. 6 weeks