Question: Time Estimates (days) Most Likely Pessimistic Optimistic Activity Start 49 95 Precedes A,B,C D E End F End End 100 C D E F 37

Time Estimates (days) Most Likely Pessimistic
Time Estimates (days) Most Likely Pessimistic Optimistic Activity Start 49 95 Precedes A,B,C D E End F End End 100 C D E F 37 80 91 25 42 62 61 98 115 49 66 80 25 48 65 What is the standard deviation of path A-D-F? 9.06 days 82 days 6,40 days 41 days 16 days