Question: TIMES ( days ) Activity Start Node Finish Node OPTIMISTIC to MOST LIKELY tm PESSIMISTIC tp A 1 2 2 6 3 8 6 2

TIMES (days)
Activity
Start Node
Finish Node
OPTIMISTIC
to
MOST LIKELY
tm
PESSIMISTIC
tp
A
1
2
26
38
62
B
1
3
16
22
34
C
2
5
14
26
62
D
3
4
32
44
68
E
4
5
15
27
51
Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: