Question: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 28 40 64 B 1
|
|
|
|
| TIMES (days) |
|
| Activity | Start Node | Finish Node | OPTIMISTIC to | MOST LIKELY tm | PESSIMISTIC tp |
| A | 1 | 2 | 28 | 40 | 64 |
| B | 1 | 3 | 16 | 22 | 34 |
| C | 2 | 5 | 17 | 29 | 65 |
| D | 3 | 4 | 30 | 39 | 66 |
| E | 4 | 5 | 15 | 33 | 51 |
Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity Ate = 42 Standard Deviation = 6 Activity Bte = Standard Deviation = Activity Cte = Standard Deviation = Activity Dte = Standard Deviation = Activity Ete = Standard Deviation = 6 Path 1 2 5 Mean Time = Standard Deviation =10 Path 1 3 4 5 Mean Time = Standard Deviation =