Question: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 28 34 46 B 1
|
|
|
|
| TIMES (days) |
|
| Activity | Start Node | Finish Node | OPTIMISTIC to | MOST LIKELY tm | PESSIMISTIC tp |
| A | 1 | 2 | 28 | 34 | 46 |
| B | 1 | 3 | 15 | 27 | 51 |
| C | 2 | 5 | 10 | 22 | 34 |
| D | 3 | 4 | 27 | 39 | 63 |
| E | 4 | 5 | 12 | 33 | 54 |
Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity Ate = 35 Standard Deviation = 3 Activity Bte =
Standard Deviation =
Activity Cte =
Standard Deviation =
Activity Dte =
Standard Deviation =
Activity Ete =
Standard Deviation = 7 Path 1 2 5 Mean Time =
Standard Deviation =5 Path 1 3 4 5 Mean Time =
Standard Deviation =
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
