Question: Topic 6 - Activity 2 A . Draw the precedence activity network using the given table. B . Calculate the earliest and latest start and

Topic 6- Activity
2
A.
Draw the precedence activity network using the given table.
B. Calculate the earliest and latest start and end dates and the float associated with each activity in the network.
C.
Write all the Paths and the critical path with duration.
\table[[Activity Name,\table[[Predecessor],[Activity List]],\table[[Activity],[duration]]],[A,,5],[B,A,7],[C,B,6],[D,A,5],[E,D,10],[F,B,15],[G,B,8],[H,G,8],[I,C,4],[J,G,4],[K,J,F,H,5],[L,K,E,I,]]