Question: Two activities on the same critical path are candidates for crashing on a network. Activity details are in the table below. Activity Normal Time Crash

Two activities on the same critical path are
Two activities on the same critical path are candidates for crashing on a network. Activity details are in the table below. Activity Normal Time Crash Time Normal Cost Crash Cost $6,000 $6,800 8 days 7 days $4,000 $5,000 10 days 8 days B a. To cut one day from the project's duration, activity(ies) should be crashed (enter a single capital letter or a sequence of capital letters in alphabetical order, separated by commas and no spaces). b. This would cost (enter a dollar amount with dollar sign: use commas if necessary)