Question: Use the backward and forward pass to find to answer the following questions: Activity Predecessor Duration (days) A 5 B 15 AB 20 D 5

Use the backward and forward pass to find to

Use the backward and forward pass to find to answer the following questions: Activity Predecessor Duration (days) A 5 B 15 AB 20 D 5 E 3 The slack time for activity A is days The slack time for activity E is days The duration of the project is days