Question: Use the data provided in the below chart and provide a network diagram containing the Early start, Early Finish, Late Start, Late Finish, Float of
Use the data provided in the below chart and provide a network diagram containing the Early start, Early Finish, Late Start, Late Finish, Float of each activity. Also highlight the critical path of the project.
| Activity | Predecessor | Estimate in months |
| Start | 0 | |
| D | Start | 4 |
| A | Start | 6 |
| F | D,A | 7 |
| E | D | 8 |
| G | F,E | 5 |
| B | F | 5 |
| H | G | 7 |
| C | H | 8 |
| End | C,B | 0 |