Question: Use the data provided in the below chart and provide a network diagram containing the Early start, Early Finish, Late Start, Late Finish, Float of

Use the data provided in the below chart and provide a network diagram containing the Early start, Early Finish, Late Start, Late Finish, Float of each activity. Also highlight the critical path of the project.

Activity Predecessor Estimate in months
Start 0
D Start 4
A Start 6
F D,A 7
E D 8
G F,E 5
B F 5
H G 7
C H 8
End C,B 0