Question: Use the data provided ir the below chart and provide a network diagram containing the Early start, Early Finish, Late Start, Late Finish, Float of

Use the data provided ir the below chart and
Use the data provided ir the below chart and
Use the data provided ir the below chart and provide a network diagram containing the Early start, Early Finish, Late Start, Late Finish, Float of each activity. Also highlight the critical path of the project. The WBS, estimates for each work package, and the network diagram are completed. What is the next thing for the project manager to do