Question: Use the information from the table to answer the questions below Activity Predecessor Duration (days) A - 7 B - 6 C A,B 11 D
Use the information from the table to answer the questions below Activity Predecessor Duration (days) A - 7 B - 6 C A,B 11 D B 5 E C,D 6.
Indicate the:
a. Identify the critical path (indicate path by series of activity letters)
b. Using forward and backward pass (diagramming not needed on answer document), indicate the:
i. Early Start and Late Start for activity D
ii. Total Float for activity D
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts